After Define Activities and Sequence Activities, the next process is:

After Define Activities and Sequence Activities, the next process is:

Question:

After Define Activities and Sequence Activities, the next process is:

Options:

Estimate Activity Resources.

Estimate Activity Durations.

Develop Schedule.

Control Schedule.

Correct Answer

The Correct Answer for this Question is

Estimate Activity Resources.