A project’s Critical Path is:

Correct Answer for the Question – A project’s Critical Path is: is given below

A project’s Critical Path is:

A sequence of activities that takes the shortest time to complete.

A sequence of activities that takes the longest time to complete.

A sequence of the activities that can be delayed without impacting the project’s end date.

A sequence of the project’s activities required to meet the defined milestones.

Correct Answer

The Correct Answer for this Question is

A sequence of activities that takes the longest time to complete.

Explanation

The Question – A project’s Critical Path is: has been answered correctly and answers for the question is A sequence of activities that takes the longest time to complete.

More about these Exams

These Exam Questions and the order of these questions keep changing. but the answers are obviously same. so if you don’t find a question after another we suggest you search it in the search box and we are sure you’ll find it. you can bookmark this site for Quick access in future.

We hope you found it helpful don’t forget to leave a comment if you feel a need to correct or ask we’re always here to help.

you can find more here at mnccertified

Feel free to contact via comment or email.

Happy Learning

Cheers, Team MNCcertified

You may also like...

Leave a Reply

Your email address will not be published. Required fields are marked *