A challenge of earned value management is predicting percent complete. The simplest formula to use to calculate EV is.

A challenge of earned value management is predicting percent complete. The simplest formula to use to calculate EV is.Multiplying the percent complete by the budget at completion, or the total budget for the project, is the simplest formula to use. The 50/50 rule, or the more conservative 0/100 rule, can eliminate the necessity for the continuous determination of percent complete. After the percent complete is determined, it can be plotted against time expended.

Question:

A challenge of earned value management is predicting percent complete. The simplest formula to use to calculate EV is.

Options:

0/100 rule

50/50 rule

(Percent complete)h budget at completion)

Milestone method

Correct Answer

The Correct Answer for this Question is

(Percent complete)h budget at completion)